You can schedule a forecast action so it runs automatically. Apply one schedule to each forecast action. 

Ensure there's already a forecast action built. 

To schedule a forecast action: 

  1. Select the Forecast action to schedule
  2.  Go to the Schedule tab and select Create schedule.
  3. Enter a Schedule name.
  4. Select the Time zone and Trigger frequency, to set how often to run the forecast.
    • Hourly
    • Daily or
    • Weekly
  5. Select how often to repeat the schedule from the Repeat every dropdown.
  6. Enter a start and end time from the Execute fields. 
  7. Select what date to activate/deactivate the Start date and End date fields. 
  8. Select Save.
    The schedule details display in the panel. Select the ellipsis to edit, deactivate, or delete the schedule.